Inflationäre Fertigungskosten ohne Preisanpassung in Langzeitverträgen

2 verified sources

Definition

Meyer Werft and Meyer Turku suffered massive losses (€180M in 2020, €103M in 2023) because contracts signed pre-pandemic did not account for post-2020 inflation in energy, raw materials, and skilled labor. No automated cost-variance alerts or contract renegotiation workflow existed.

Key Findings

  • Financial Impact: €180 million (2020 Meyer Werft); €103 million (2023 Meyer Turku). Estimated annual industry bleed: €150-200M across German naval/cruise builders.
  • Frequency: Recurring annually; worsens when macroeconomic shocks hit (pandemics, war, sanctions).
  • Root Cause: Fixed-price contract terms + manual cost tracking + 3-5 year production cycles + lack of real-time escalation clause enforcement.

Why This Matters

This pain point represents a significant opportunity for B2B solutions targeting Shipbuilding.

Affected Stakeholders

Procurement managers, Contract administrators, Naval acquisition officers (Beschaffungsamt für Wehrtechnik und Logistik), Finance controllers

Deep Analysis (Premium)

Financial Impact

Financial data and detailed analysis available with full access. Unlock to see exact figures, evidence sources, and actionable insights.

Unlock to reveal

Current Workarounds

Financial data and detailed analysis available with full access. Unlock to see exact figures, evidence sources, and actionable insights.

Unlock to reveal

Get Solutions for This Problem

Full report with actionable solutions

$99$39
  • Solutions for this specific pain
  • Solutions for all 15 industry pains
  • Where to find first clients
  • Pricing & launch costs
Get Solutions Report

Methodology & Sources

Data collected via OSINT from regulatory filings, industry audits, and verified case studies.

Evidence Sources:

Related Business Risks

Massive Zahlungsverzögerung durch 80% Nachzahlungsmodell bei Schiffsabnahme

€2.8 billion immediate funding gap. Estimated annual financing cost: €140-200M (5% interest on €2.8B working capital). Industry-wide estimated bleed: €400-600M annually across all major German shipyards.

Kapazitätsverlust durch regulatorische Überlastung (2/3 der Industrie vernichtet)

Estimated €2-3 billion in cumulative lost contract value annually. Typical compliance admin = 40% of contract price (per VSM); competitors charge 5-10%. Overage = 30-35% price premium per contract = 20-30% market share loss to competitors.

Fehlende digitale Compliance-Nachweise in Rüstungsbeschaffung (Betriebsprüfungsrisiko)

Estimated €10-50M per major audit failure; industry-wide annual bleed: €20-100M. Typical penalty: €5,000-€50,000 per non-compliant invoice/filing per Finanzamt guidelines.

Beschaffungsverfahren-Overhead bei Regierungsaufträgen (Rüstungsbeschaffung)

€40 per €100 of contract value (40% of purchase price); typical German naval shipbuilding contract: €50–200M → €20–80M in process costs annually across major yards

GoBD-Konformitätsrisiken bei unstrukturierter GFE-Nachverfolgung

€5,000–€50,000 per audit finding (average); repeat violations: €100,000–€1,000,000+; estimated 15–25% of German shipyards non-compliant per IDW audit surveys

Verzögerter Zahlungseingang durch manuelle GFE-Verifizierung bei Regierungsverträgen

€2–5M working capital per €50–100M contract; 30–90 days cash flow delay; estimated cost of capital: 4–6% annually on delayed invoices

Request Deep Analysis

🇩🇪 Be first to access this market's intelligence