🇦🇪UAE

خسارة الاستحقاق بسبب عدم الامتثال لفترة الإخطار بالتغييرات (Loss of Entitlement Due to Variation Notice Non-Compliance)

2 verified sources

Definition

Change orders submitted without formal notice within the 28-day contractual window result in complete loss of entitlement to payment. Search results indicate that 'Failure to issue timely notice may result in a loss of entitlement, regardless of the validity of the claim.' Manual processes lack automated deadline tracking.

Key Findings

  • Financial Impact: AED 100,000–500,000 per forfeited change order (100% loss of claimed variation cost)
  • Frequency: Estimated 1–3 times per project lifecycle (per 5–10 change orders typical on AED 10M+ projects)
  • Root Cause: Absence of centralized change order register with deadline alerts; reliance on manual submission workflows without system-enforced timelines

Why This Matters

This pain point represents a significant opportunity for B2B solutions targeting Residential Building Construction.

Affected Stakeholders

Cost Managers, Project Managers, Site Engineers, Contractors

Deep Analysis (Premium)

Financial Impact

Financial data and detailed analysis available with full access. Unlock to see exact figures, evidence sources, and actionable insights.

Unlock to reveal

Current Workarounds

Financial data and detailed analysis available with full access. Unlock to see exact figures, evidence sources, and actionable insights.

Unlock to reveal

Get Solutions for This Problem

Full report with actionable solutions

$99$39
  • Solutions for this specific pain
  • Solutions for all 15 industry pains
  • Where to find first clients
  • Pricing & launch costs
Get Solutions Report

Methodology & Sources

Data collected via OSINT from regulatory filings, industry audits, and verified case studies.

Evidence Sources:

Related Business Risks

تأخير الموافقة على أوامر التغيير يؤدي إلى تمديد الجدول الزمني والتكاليف الإضافية (Change Order Approval Delays Causing Schedule Extension & Cost Overruns)

AED 50,000–200,000 per day of delay × 5–10 days typical = AED 250,000–2,000,000 per change order

تسريب الإيرادات من أوامر التغيير غير المسجلة والفواتير المفقودة (Revenue Leakage from Untracked Change Orders and Lost Invoices)

AED 200,000–1,500,000 per project (2–5% of typical AED 10M–30M project variation costs)

الاختناقات اليدوية في معالجة أوامر التغيير وتأخير تنفيذ المشاريع (Manual Processing Bottlenecks & Project Execution Delays)

AED 3,000–12,000 per change order in manual labor (20–40 hours × AED 150–300/hour labor cost)

تأخير الدفع بسبب عدم الموافقة على التغييرات والفواتير المعلقة (Payment Delays from Unapproved Changes & Suspended Invoices)

AED 500,000–2,000,000+ per month per active project (weighted by invoice volume and AR days extension)

قرارات شراء وتخصيص موارد خاطئة بسبب نقص البيانات المركزية (Poor Procurement & Resource Allocation Decisions Due to Lack of Visibility)

AED 100,000–500,000 per project (2–4% material waste + 20–30% rush order premium on change-driven procurements)

تجاوز التكاليف ونقص تتبع الميزانية

2-5% cost overruns annually (AED 3.8-9.5 billion across UAE market of AED 189.59 billion); typical project: AED 500,000-2,000,000 per project overage